ERROR :Enter an Activity number. The require Activity number for Expense forecast is marked in Project. In AX2012

When user want to create a Expenses Forecast in project.
System give an error as shown below ;
“Enter an Activity number. The require Activity number for Expense forecast is marked in Project.”
2016-05-09_16-15-13

Solution :

The above error comes in project module, due to activity check at parameter ”

Path : project management -> SETUP – > Project Management & Accounting Parameter.
erroe1

Uncheck the below checkbox.
error2

error3

Leave a Reply